After nine and one half years of intense battling, during
which the ICP put a tremendous effort, the Section 700 Expressway
Project on US 202 running from Doylestown to Montgomeryville
in Southeastern Pennsylvania is dead.
On Wednesday, February 16, 2005, Pennsylvania’s
Secretary of Transportation, Allen Biehler held a series of
meetings in Harrisburg to announce PennDOT’s findings
of a supplemental study that was stimulated by an alternative
plan submitted by the Neighbors for Bucks County Preservation
and by intense lobbying by opponents to the expressway. The
results of PennDOT’s study shocked many expressway proponents
but only confirmed what opponents have been saying for years:
that the proposed expressway would not have relieved congestion
along the 202 corridor and would have increased development
and traffic volumes in the region.
Secretary Biehler was extremely clear on two
points:
1.) The expressway, as approved, would not have
had a significant impact on congestion;
2.) There are no funds to build the expressway
even if it did all that was promised to the public.
In place of the four-lane expressway, PennDOT
is proposing a two-lane parkway that would utilize the right-of-way
obtained by the expressway and approximately $40 million in
improvements along the existing 202 corridor. The revised
plan was met with cautious optimism from both sides of the
expressway controversy.
The information provided below is derived from
the meeting with the Secretary of Transportation and the short
handout provided by PennDOT. As such, it should be recognized
that no one currently has the details necessary to intelligently
say aye or nay to the concept.
1. Three meetings were held concerning 202.
The first involved legislators from the region, which was
followed by separate meetings with pro-expressway municipalities
and those opposed to the expressway.
2. Secretary of Transportation, Allen Biehler
and Tim Jackson, of Gladding/Jackson, the firm commissioned
by PennDOT to restudy 202, were the primary speakers. Both
asserted that there were insufficient funds for the project
and that the project goals of congestion relief would not
be realized even if the project were constructed.
3. It was acknowledged that the new study was based on the
Delaware Valley Regional Planning Commission (DVRPC) traffic
counts and projections, as was the original study. Interestingly,
the conclusions drawn from the two studies are quite different.
This raises the very important question of who knew what and
when.
Why is this important? Because $84 million of
taxpayers’ money has been spent on a project that was
never going to work as claimed. Under other circumstances,
perhaps those involved in the project could claim that new
information and technologies resulted in the differing conclusions.
However, in this instance, Gladding/Jackson’s findings
mirror those of Buckingham, which sent up the red flag as
early as 1995.
How is it possible that several municipal officials
were able to correctly identify the fatal flaws with the expressway
proposal and swarms of transportation professionals were not?
Even worse, Buckingham officials were extremely open about
the problems that they identified and provided extensive documentation
as to the cause and impact of the project deficiencies that
were totally ignored and/or discounted. How did this happen?
There appear to be only two potential answers and it will
be very interesting to find out which one is correct:
A. Incompetence on the part of PennDOT, DVRPC,
FHWA and the engineering firms assigned to the expressway
project.
B. Manipulation of the process for some purpose
other than the stated project goal.
To be blunt, if #2 is the correct answer, then
one or more people knew that the project would not work as
promised and allowed $84 million of our money to be wasted.
We cannot imagine that anyone in a corporate setting would
be allowed to get away with wasting $84 million on a project
doomed to failure and retain their position. We see no reason
why the same standards should not apply to government officials
as well.
Again, the question comes down to who knew what
when? If they didn’t know at all, that is just as bad!
4. As predicted in 1996 by Buckingham, Tim Jackson
confirmed that building the expressway would increase the
amount of travel in the 202 corridor by approximately 33%.
To those who continue to support the expressway, the following
question remains open and unanswered… how do you hope
to reduce congestion by significantly increasing traffic?
5. As previously predicted, PennDOT confirmed that the vast
majority of the traffic on 202 was local in nature. This is
a direct contradiction to claims made by expressway proponents
who have, for years, placed the blame for their congestion
on non-resident pass through trips. According to the report,
202 traffic is comprised of:
7% regional / through trips
37% begin or end in the study area
56% are completely local, beginning AND ending in the study
area
6. The parkway plan includes 12 at-grade intersections. The
expressway called for only three elevated interchanges. By
increasing the number of entry and exit points, the parkway
provides for far greater mobility within the corridor.
7. The parkway would be built following the contours of the
land. This would help minimize the environmental impact and
make it very difficult (though not impossible) to replace
the two- lane parkway with a four-lane expressway in the future.
8. The construction techniques required by the two road types
are very different. Although building a two-lane road that
follows the contours does not totally preclude expanding it
to an expressway in the future, it is very likely that the
parkway would have to be removed to do so. That cost, combined
with the need to add bridges and interchanges plus resident
anger at having their newly acquired local travel routes reduced
once again, make future expansion unlikely. That said, both
Buckingham and Solebury recognize the potential for expansion
and it is expected that they will make reducing that possibility
a high priority in the negotiations.
9. Eugene McGill, a State Representative from Montgomery County
has been crowing that the Smart Mobility plan was shown to
be ineffective. That is not correct. We can expect to see
major components of the plan in the final solution including
roundabouts, improvements to existing 202, and alternate routes.
Rather than gloating, Mr. McGill would have been better served
thanking those who worked so hard on Smart Mobility for their
efforts to improve the regional transportation. We don’t
take Mr. McGill too seriously and would remind readers that
he is the legislator who recently referred to residents of
Buckingham and Solebury as “ignorant” in the Philadelphia
Inquirer.
10. Secretary Biehler stressed that access to the new parkway
would be limited and that driveways (commercial and residential)
would not be allowed. This is a good first step but the affected
municipalities must implement proper land use planning as
well. If the new road is allowed to be developed along the
same lines as 202 or 309 in Chalfont, New Britain and Montgomeryville
have been, then the new road will fail and $200 million dollars
will have been wasted. There will be a great deal of pressure
to allow intense development along the new road and it is
the responsibility of the community to make sure that their
local governments do not sell out or cave-in to the developers
who are certain to be banging on the door.
11. The approved expressway plan did not include any funding
for improvements along the existing 202 corridor. The parkway
concept does. This is a major change and one that is welcome
due to the significant benefit that will be realized immediately.
Buckingham and Solebury both suggested to the Secretary that
these improvements be begun as soon as possible and not be
delayed by the planning process that must accompany the parkway.
12. The expressway proposal was originally projected to cost
$225 million. It is currently estimated at over $460 million
– a 100% plus increase. The cause of this increase was
not delays caused by Buckingham and Solebury but rather the
initial estimate was grossly inaccurate. In point of fact,
the opposition to the expressway never tried to and did not
delay the project by even a minute until last spring. At that
point, PennDOT, at the request of multiple municipalities
agreed to explore other alternatives and this was the only
period of time that the project was on hold in ANY manner.
That process took approximately 10 months and we doubt that
anyone can make an intelligent case for the cost of the project
increasing by $235 million in that short timeframe.
13. Buckingham and Solebury have requested that Demand Reduction
strategies be considered inclusive of park and ride lots,
corporate jitneys and other methods to reduce the number of
cars on our roads. PennDOT officials responded favorably and
we are hopeful that opportunities to reduce the number of
vehicles will be seriously evaluated.
14. The parkway will have a limited impact on the congestion
on existing 202 as the vast majority of that traffic is local
and the zoning along the route encourages ever-increasing
automobile usage.
15. Traffic volumes on existing 202 are down but congestion
has increased. There are very simple reasons why that is occurring
and will continue to occur. All communities in the region
need to take a very hard look at their zoning and make fundamental
decisions about what they want their communities to be like
in the future. This cannot be a fantasy exercise because with
each decision comes ramifications and those ramifications
are very real.
For example, is anyone really surprised that PA 611 in Doylestown
and Warrington has become a traffic nightmare? One look at
the retail construction tells you why it is happening. We
are not saying that the type of development that the community
has chosen to allow is necessarily bad, merely that by choosing
that form of development certain secondary impacts are assured
to occur. If you are going to encourage development forms
that require auto access for success (i.e. retail), don’t
be surprised when you get cars.
|